โœ•

PMPยฎ Master Dump Sheet

Complete Brain Dump ยท Cheat Sheet ยท Exam Tips ยท Keyword Reference ยท Study Tracker

PMBOKยฎ 7th Ed ECO 2021 Predictive + Agile + Hybrid 180 Questions 230 Minutes

๐Ÿ“Œ Exam Overview

Exam Format & Key Facts

ItemDetail
Questions180 total (5 are unscored pretests)
Time230 minutes (โ‰ˆ1 min 17 sec/question)
Breaks2 optional 10-min breaks (timer stops)
FormatMultiple choice, drag-drop, matching, hotspot, limited choices
Pass/FailNo fixed pass score โ€” proficiency levels per domain
Split~50% Predictive / ~50% Agile & Hybrid
Experience Required36 months PM (degree) or 60 months (no degree)
PDUs60 PDUs every 3 years to maintain
๐Ÿ”ด EXAM TIP: The PMP is not just PMBOK! Expect heavy Agile/Scrum scenarios. When in doubt, choose the answer that "talks to the team first," "updates the plan," or "looks at the root cause."

Three ECO Domains (2021)

Domain% of ExamFocus
1 โ€” People42%Leading teams, conflict, communication, stakeholders
2 โ€” Process50%Project execution, planning, predictive & agile methods
3 โ€” Business Environment8%Strategy, compliance, benefits, organizational change

๐Ÿ‘ฅ Domain 1 โ€” People (42%)

Leadership Styles

StyleWhen to UseKey Signal Words
Servant LeaderAgile / Scrum Master role; team is self-organizing"Remove obstacles," "serve team," "facilitate"
TransactionalRoutine tasks; rewards/penalties tied to performance"Reward," "penalty," "carrot/stick"
TransformationalInnovation, change, inspire vision"Inspire," "vision," "motivate," "change"
Laissez-FaireHighly skilled, self-directed team โ€” minimal oversight"Hands-off," "trust experts"
Autocratic / DirectingCrisis, safety, emergency โ€” quick decision needed"Emergency," "crisis," "no time for consensus"
Democratic / ParticipativeComplex problems needing team input"Vote," "team decision," "consensus"
CoachingDeveloping team skills; junior team members"Mentor," "develop skills," "grow"
CharismaticOrganizational rallying, morale boost"Enthusiasm," "energy," "followers"
InteractionalBalance of task, relationship, and change"Mix of styles"
๐Ÿ”ด EXAM TIP: The PMP LOVES servant leadership. If a question mentions Agile/Scrum and asks "what should the PM do?" โ€” servant leadership is almost always the answer.

Conflict Management (Thomas-Kilmann)

MethodWin/LoseBest When
Collaborate / Problem-SolveWin-Win โœ… BESTEnough time; long-term relationship; complex issue
Compromise / ReconcileLose-Lose / Some-SomeTime pressure; equal power; temporary fix
Smoothing / AccommodatingLose-WinRelationship preservation; issue is minor for you
Forcing / DirectingWin-Lose โŒ WORSTEmergency; you have authority; safety issue
Withdrawal / AvoidingLose-LoseGather more data; let parties cool down
๐Ÿ’ก TIP: Conflict resolution order on PMP: 1) Collaborate โ†’ 2) Compromise โ†’ 3) Smoothing โ†’ 4) Forcing โ†’ 5) Withdrawal. Always try problem-solving FIRST.
๐Ÿ“˜ SCENARIO: Two team members disagree on technical approach. PM should โ†’ Meet with both to understand each perspective and work toward a solution everyone accepts (Collaborate).

Motivation Theories

TheoryKey ConceptExam Trigger Words
Maslow's Hierarchy5 levels: Physiologicalโ†’Safetyโ†’Socialโ†’Esteemโ†’Self-ActualizationNeeds hierarchy, pyramid
Herzberg's Two-FactorHygiene factors (prevent dissatisfaction) vs Motivators (increase satisfaction)Salary alone won't motivate; recognition does
McGregor X & YTheory X = people dislike work (need control); Theory Y = people are motivated, self-directed"Micromanage" vs "trust team"
Vroom's ExpectancyMotivation = Expectancy ร— Instrumentality ร— ValenceEffortโ†’Performanceโ†’Reward chain
McClelland's NeedsNeed for Achievement, Affiliation, Power"This person thrives on competition/relationships/control"
Ouchi's Theory ZJapanese style: lifetime employment, collective decision-making, holistic concernLong-term loyalty, company as family

Team Development โ€” Tuckman's Model

StageWhat HappensPM Action
FormingPolite, uncertain, getting to know each otherDirect, set goals, establish norms
StormingConflict, power struggles, frustrationCoach, mediate, resolve conflict
NormingAgreement, rules established, cohesion buildsSupport, facilitate, praise
PerformingHigh performance, self-directed, productiveDelegate, trust, servant leadership
AdjourningProject ending, team disbandsCelebrate, lessons learned, recognize
๐Ÿ”ด EXAM TIP: Exam loves Tuckman! "Team arguing about roles" = Storming. "Team producing great results independently" = Performing.

Communication

Communication Channels Formula: N ร— (N-1) / 2 where N = number of stakeholders

Example: 10 stakeholders โ†’ 10 ร— 9 / 2 = 45 channels
Adding 1 person to team of 10 โ†’ goes from 45 to 55 channels (+10 new channels)
๐Ÿ”ด EXAM TIP: PM spends ~90% of time communicating. Important communications = Formal Written. Quick coordination = Interactive. Large one-way = Push.

Stakeholder Management

GridQuadrantStrategy
Power/InterestHigh Power, High InterestManage Closely โœ…
High Power, Low InterestKeep Satisfied
Low Power, High InterestKeep Informed
Low Power, Low InterestMonitor

Stakeholder Engagement Levels:

โš™๏ธ Domain 2 โ€” Process (50%)

Predictive / Waterfall Approach

5 Process Groups (PMBOK 6th โ€” Still Tested)

Process GroupKey Documents Created% Focus
1. InitiatingProject Charter, Stakeholder RegisterStart Here
2. PlanningProject Management Plan, all subsidiary plans, WBS, Schedule, BudgetMost documents
3. ExecutingDeliverables, Change Requests, Work Performance DataMost $$ spent
4. Monitoring & ControllingWork Performance Reports, Change Requests, ForecastsRuns entire project
5. ClosingFinal Report, Lessons Learned, Closed ContractsFormal acceptance
๐Ÿ”ด EXAM TIP: M&C runs throughout the entire project, not just at the end! If you see "comparing actual to planned," it's M&C.

10 Knowledge Areas

Integration ยท Scope ยท Schedule ยท Cost ยท Quality ยท Resource ยท Communications ยท Risk ยท Procurement ยท Stakeholder

๐Ÿ“˜ Mnemonic: I Saw Some Cool Quality Resources Communicating Risk Procurement Stakeholders
KAKey PlansKey Processes
IntegrationPM Plan, Project CharterDevelop Charter, Develop PM Plan, Direct & Manage, Monitor, Close
ScopeScope Management PlanCollect Requirements, Define Scope, Create WBS, Validate Scope, Control Scope
ScheduleSchedule Management PlanDefine Activities, Sequence, Estimate Durations, Develop Schedule, Control
CostCost Management PlanPlan, Estimate, Determine Budget, Control Costs
QualityQuality Management PlanPlan Quality, Manage Quality, Control Quality
ResourceResource Management PlanPlan, Estimate, Acquire, Develop Team, Manage Team, Control
CommunicationsCommunications Management PlanPlan, Manage, Monitor Communications
RiskRisk Management Plan, Risk RegisterPlan, Identify, Qualitative, Quantitative, Plan Responses, Implement, Monitor
ProcurementProcurement Management PlanPlan, Conduct, Control Procurement
StakeholderStakeholder Engagement PlanIdentify, Plan, Manage, Monitor Stakeholder Engagement

Agile / Scrum Framework

๐Ÿ”„ Scrum Roles

  • Product Owner โ€” owns backlog, priorities
  • Scrum Master โ€” servant leader, removes impediments
  • Development Team โ€” self-organizing, cross-functional

๐Ÿ“… Scrum Events

  • Sprint โ€” 1-4 week iteration
  • Sprint Planning โ€” what & how
  • Daily Scrum โ€” 15-min standup
  • Sprint Review โ€” demo to stakeholders
  • Sprint Retrospective โ€” improve process

๐Ÿ“ฆ Scrum Artifacts

  • Product Backlog โ€” all features (PO owns)
  • Sprint Backlog โ€” selected for sprint
  • Increment โ€” working software
  • Definition of Done โ€” quality standard

๐Ÿ“Š Agile Metrics

  • Velocity โ€” story pts per sprint
  • Burndown Chart โ€” work remaining
  • Burnup Chart โ€” work completed
  • Cycle Time โ€” start to done
  • Lead Time โ€” request to done

Agile Values (Agile Manifesto)

We value...Over...
Individuals and interactionsProcesses and tools
Working softwareComprehensive documentation
Customer collaborationContract negotiation
Responding to changeFollowing a plan
๐Ÿ”ด EXAM TIP: Agile doesn't mean NO documentation โ€” it means LESS is MORE. Working software is the primary measure of progress in Agile.

Kanban Key Concepts

Hybrid Approach

๐Ÿ“˜ SCENARIO: Construction project with software component โ€” use predictive for physical construction (regulated), agile for software development (uncertain requirements).

Risk Management

StepOutputKey Tool
Plan Risk ManagementRisk Management PlanMeetings
Identify RisksRisk Register, Risk ReportBrainstorming, SWOT, Checklists, Delphi
Qualitative AnalysisUpdated Risk RegisterProbability ร— Impact Matrix
Quantitative AnalysisNumeric risk dataMonte Carlo, Decision Tree, EMV
Plan Risk ResponsesRisk Response PlanSee strategies below
Implement ResponsesChange RequestsRisk Register updates
Monitor RisksWork Performance InfoAudits, Reserve Analysis

Risk Response Strategies

TypeThreats (Negative)Opportunities (Positive)
Eliminate/ExploitAvoid โ€” change plan to eliminateExploit โ€” ensure it happens
Reduce/EnhanceMitigate โ€” reduce prob/impactEnhance โ€” increase prob/impact
Transfer/ShareTransfer โ€” insurance, contractShare โ€” partner/alliance
AcceptAccept โ€” active (contingency) or passive (budget)
EscalateEscalate โ€” beyond project scope, goes to program/portfolio
Expected Monetary Value (EMV):
EMV = Probability ร— Impact ($)
Example: 30% chance of losing $10,000 โ†’ EMV = -$3,000
Example: 40% chance of gaining $5,000 โ†’ EMV = +$2,000
๐Ÿ’ก TIP: Contingency Reserve = known unknowns (identified risks) | Management Reserve = unknown unknowns (unforeseen events). PM controls contingency; sponsor approves management reserve.

Quality Management

ConceptDefinition
Grade vs QualityGrade = category of features. Quality = meeting requirements. Low grade โ‰  low quality (a budget hotel can have high quality if it meets spec)
Prevention over InspectionBuild quality in โ€” don't just inspect it out. Cost of Prevention < Cost of Correction
Gold PlatingAdding extras not in scope โ€” BAD! Only deliver what is required
Cost of Quality (COQ)Prevention + Appraisal + Internal Failure + External Failure
Six Sigma (6ฯƒ)99.99966% defect-free; 3ฯƒ = 99.73%

Quality Tools (7 Basic)

๐Ÿ”ด EXAM TIP โ€” Rule of Seven: 7 consecutive data points on same side of mean in control chart = process is out of control even if within limits!

Procurement & Contracts

Contract TypeBuyer RiskSeller RiskWhen to Use
Fixed Price (FFP)LowHighScope well-defined; buyer wants certainty
FP-EPAMediumMediumLong duration; inflation adjustment
FPIFMedium-LowMediumIncentivize performance; some uncertainty
T&M / TMCRHighLowScope uncertain; short duration
CPFFHighLowR&D, exploratory; scope very uncertain
CPIFMedium-HighLow-MediumMotivate cost control
CPAFHighLowSubjective performance award
๐Ÿ”ด EXAM TIP: Buyer risk increases as you go from Fixed Price โ†’ T&M โ†’ Cost Plus. Seller risk is highest in Fixed Price.

Change Management

๐Ÿข Domain 3 โ€” Business Environment (8%)

Benefits Realization

Compliance & Governance

PMO TypeAuthority LevelRole
SupportiveLow (Consultative)Provides templates, training, lessons learned
ControllingMediumRequires compliance with frameworks; audits
DirectiveHighDirectly manages projects; PMs report to PMO

Strategic Alignment & Org Structures

StructurePM AuthorityResource Control
FunctionalLittle/NoneFunctional Manager
Weak MatrixLimitedFunctional Manager
Balanced MatrixLow-MediumMixed (shared)
Strong MatrixMedium-HighPM has more control
ProjectizedHighPM
Composite/HybridVariesMixed
๐Ÿ”ด EXAM TIP: Functional org = PM has LEAST power. Projectized org = PM has MOST power. Matrix = middle ground with conflicts over resources.

๐Ÿงฎ Key Formulas โ€” EVM & More

Earned Value Management (EVM)

TermFormulaMeaning
PV โ€” Planned ValueBudget allocated for work scheduledWhat should have been done
EV โ€” Earned Value% Complete ร— BACValue of work actually done
AC โ€” Actual CostActual money spentWhat it actually cost
BAC โ€” Budget at CompletionTotal project budgetOriginal approved budget
Variance Analysis:
CV (Cost Variance) = EV โˆ’ AC    [+ = under budget, โˆ’ = over budget]
SV (Schedule Variance) = EV โˆ’ PV    [+ = ahead, โˆ’ = behind]

Performance Indices:
CPI (Cost Performance Index) = EV / AC    [>1 = good, <1 = over budget]
SPI (Schedule Performance Index) = EV / PV    [>1 = ahead, <1 = behind]

Forecasts:
EAC (Estimate at Completion) โ€” 4 formulas:
  1. EAC = BAC / CPI (if current trend continues)
  2. EAC = AC + ETC (new estimate for remaining)
  3. EAC = AC + (BAC โˆ’ EV) (if current variance is atypical)
  4. EAC = AC + [(BAC โˆ’ EV) / (CPI ร— SPI)] (both impact forecast)

ETC (Estimate to Complete) = EAC โˆ’ AC
VAC (Variance at Completion) = BAC โˆ’ EAC
TCPI = (BAC โˆ’ EV) / (BAC โˆ’ AC)    [must achieve this CPI to hit BAC]
๐Ÿ“˜ EVM Example: BAC=$100K, 40% complete, AC=$50K
EV = 40% ร— $100K = $40K | CV = $40K โˆ’ $50K = โˆ’$10K (over budget!) | CPI = 40/50 = 0.80 (spending $1.25 for every $1 of value)

Other Key Formulas

Communication Channels: N(Nโˆ’1)/2
PERT (3-Point Estimate): (O + 4M + P) / 6
PERT Standard Deviation: (P โˆ’ O) / 6
PERT Variance: [(P โˆ’ O) / 6]ยฒ
Float / Slack: LS โˆ’ ES or LF โˆ’ EF
Critical Path: Longest path (zero float)
ROI: (Benefit โˆ’ Cost) / Cost ร— 100%
NPV: Higher NPV = preferred project (select highest)
IRR: Higher IRR = preferred project (select highest)
Payback Period: Shorter = preferred (select shortest)
Benefit-Cost Ratio (BCR): >1 = beneficial; > = better
๐Ÿ”ด EXAM TIP โ€” Project Selection: NPV highest = best. IRR highest = best. Payback period shortest = best. BCR >1 = viable. If NPV = $0, the IRR equals the discount rate.

๐Ÿ“‚ ITTO Highlights (Must-Know)

๐Ÿ“˜ ITTO = Inputs, Tools & Techniques, Outputs โ€” You don't need to memorize all 49 processes' ITTOs, but know the key patterns below.
ProcessKey InputKey ToolKey Output
Develop Project CharterBusiness Documents, AgreementsExpert Judgment, MeetingsProject Charter
Identify StakeholdersProject Charter, AgreementsStakeholder Analysis, Power/Interest GridStakeholder Register
Develop PM PlanProject Charter, Outputs from planningExpert Judgment, Meetings, ChecklistProject Management Plan
Collect RequirementsCharter, Stakeholder RegisterInterviews, Focus Groups, Surveys, DelphiRequirements Documentation, Traceability Matrix
Create WBSScope Statement, Req. DocumentationDecomposition, Expert JudgmentWBS, WBS Dictionary, Scope Baseline
Develop ScheduleActivity list, Network diagram, Resource calendarsCPM, CCM, PERT, Resource LevelingSchedule Baseline, Project Schedule
Identify RisksPM Plan, Stakeholder Register, Project DocsBrainstorming, SWOT, Checklists, DelphiRisk Register, Risk Report
Control QualityProject Docs, Deliverables, Work Perf. Data7 QC Tools, Testing, InspectionQuality Control Measurements, Verified Deliverables
Close Project/PhasePM Plan, Accepted Deliverables, Project DocsExpert Judgment, Meetings, Data AnalysisFinal Report, Lessons Learned, Closed Contracts

Key ITTO Patterns to Remember

โš–๏ธ Ethics & Professional Conduct (PMI Code)

4 Core Values

๐ŸŽฏ Responsibility

Take ownership; report issues; honor commitments; follow through

๐Ÿค Respect

Value others' perspectives; avoid harassment; give credit

โš–๏ธ Fairness

Make unbiased decisions; disclose conflicts of interest; be transparent

โœ… Honesty

Don't lie, deceive, or manipulate; communicate truthfully

Common Ethics Scenarios on Exam

SituationCorrect Action
Team member doing something unethicalConfront directly first, then escalate if not resolved
Sponsor pressures you to hide schedule slipRefuse; report accurate status regardless of politics
Offered a gift from vendorDecline (or follow organizational policy) โ€” avoid conflict of interest
Discover competitor's confidential infoDo not use it; inform management; discard
You make a mistake that causes problemsReport it immediately; take responsibility; correct it
Asked to falsify reportsAbsolutely refuse; escalate to PMO/sponsor/ethics hotline
๐Ÿ”ด EXAM TIP: Ethics questions = always choose the most HONEST and TRANSPARENT option. Never choose to hide information, ignore problems, or act in self-interest.

โšก Final Cheat Sheet โ€” Must-Know

Golden Rules โ€” Always True on PMP

Top Exam Tips & Tricks

๐Ÿ”ด Q: Conflict arises in team? โ†’ First: address directly with parties involved. Then: escalate if unresolved.
๐Ÿ”ด Q: Project is over budget? โ†’ Analyze CPI, find root cause, create EAC, present options to sponsor. Do NOT simply cut scope without CCB.
๐Ÿ”ด Q: Stakeholder wants change? โ†’ Evaluate impact, submit Change Request, wait for CCB. Even sponsor must go through CCB for baseline changes.
๐Ÿ”ด Q: Team member underperforming? โ†’ Coach first; document; HR is last resort. Performance issues go: Coaching โ†’ Training โ†’ HR โ†’ Replace.
๐Ÿ”ด Q: Risk was not identified and just happened? โ†’ It's now an Issue. Implement a Workaround. Update Risk Register and Lessons Learned.
๐Ÿ”ด Q: Vendor delivers late? โ†’ Refer to contract terms first. Check procurement management plan. Communicate formally.
๐Ÿ”ด Q: Scope creep happening? โ†’ Say NO without a change request. Refer to scope statement. Submit CR if stakeholder insists.
๐Ÿ”ด Q: Team in new country/culture? โ†’ Use Cultural Intelligence; learn norms; avoid assumptions; adapt communication style.
๐Ÿ”ด Q: "What should the PM do FIRST?" โ†’ Check the plan, assess impact, communicate. Never jump to executing a solution without analysis.
๐Ÿ”ด Q: Project is in Agile โ€” impediment exists? โ†’ Scrum Master removes impediments. PM / SM facilitate; team self-organizes.

๐Ÿ“˜ Keyword Index (Click to See Definition)

Click any keyword for a quick explanation:

Servant Leader CCB WBS Baseline Scope Creep Gold Plating Critical Path Float/Slack Fast Tracking Crashing Contingency Reserve Management Reserve EVM CPI SPI BAC EAC ETC PMO Sprint Retrospective Velocity Definition of Done Burndown Chart WIP Limit Fishbone Diagram Pareto Chart Control Chart PERT Delphi Technique Risk Register Workaround Integrated Change Control Lessons Learned Project Charter Business Case Triple Constraint Six Sigma Fixed Price (FFP) T&M Contract Maslow's Hierarchy Collaborate Forming Stage Storming Stage Product Owner Scrum Master Projectized Org Functional Org NPV TCPI EMV Cultural Intelligence Cost of Quality Prevention over Inspection

โœ… Study Tracker โ€” Track Your Progress (Auto-Saved)

Topics Completed:

โœ“ Progress Saved