📗 PMP CHEAT SHEET — PART 2
PMBOK 7th Ed · Org Structures · Financial Analysis · Advanced Agile · Interpersonal Skills · 20 New Scenarios
📘 PMBOK 7th Edition — 12 PM Principles
PMBOK 7 shifted from process-based to principle-based. These 12 principles guide PM behavior and decision-making. Heavily tested!
| # | Principle | Key Idea |
| 1 | Stewardship | Act with integrity; care for all resources |
| 2 | Collaborative Team | Build trust, shared goals, inclusion |
| 3 | Stakeholder Engagement | Identify, involve, and manage stakeholders proactively |
| 4 | Focus on Value | Everything done should deliver business value |
| 5 | Systems Thinking | Projects are systems — changes have cascading effects |
| 6 | Leadership | Lead by example; adapt style to situation |
| 7 | Tailoring | No one-size-fits-all; adapt methods to context |
| 8 | Quality | Quality built in, not inspected in |
| 9 | Navigate Complexity | Anticipate and address ambiguity proactively |
| 10 | Optimize Risk | Balance threats and opportunities continuously |
| 11 | Adaptability | Respond to change; recover from disruption |
| 12 | Enable Change | Help stakeholders embrace change, not resist it |
💡 Tip: PMBOK 7 principles are NOT prescriptive steps — they are guiding values. Exam questions will test whether you apply the right principle in context.
🎯 PMBOK 7 — 8 Performance Domains
Performance Domains replace Knowledge Areas in PMBOK 7. They are interacting areas of focus that work simultaneously throughout the project.
| Domain | Focus | Key Outcomes |
| Stakeholder | Productive relationships | Stakeholders engaged; needs understood |
| Team | High-performing team culture | Shared ownership, trust, results |
| Dev Approach & Life Cycle | Right method for the project | Appropriate cadence and phases |
| Planning | Organized, coordinated effort | Realistic schedule, budget, scope |
| Project Work | Efficient project execution | Focus, flow, performance |
| Delivery | Value delivered on time | Deliverables meet requirements |
| Measurement | Performance tracked and optimized | Informed decisions; timely response |
| Uncertainty | Risk and ambiguity managed | Resilience; threat/opportunity balance |
✅ Key Shift: PMBOK 6 = "What processes to follow." PMBOK 7 = "What outcomes to achieve." The exam now focuses on outcomes and judgment, not memorizing process inputs/outputs.
✂️ Tailoring
Tailoring = selecting and adapting the right methods, tools, and approaches for each unique project.
What Gets Tailored?
- Life cycle approach (predictive vs agile vs hybrid)
- Processes selected (not all processes are needed on every project)
- Documents and artifacts
- Meeting cadence and reporting frequency
- Tools and techniques
Tailoring Considerations
| Factor | Tailoring Direction |
| High uncertainty / evolving requirements | → More agile / adaptive |
| Regulatory / compliance requirements | → More predictive / documentation-heavy |
| Small experienced team | → Lighter processes |
| Large distributed team | → More formal communication plans |
| Safety-critical project | → More quality gates and audits |
💡 Tip: Tailoring is NOT doing whatever you want. It must align with organizational standards and PMO guidelines.
🗂️ Models, Methods & Artifacts (PMBOK 7)
Commonly Tested Models
| Model | What It Explains |
| Situational Leadership (Hersey-Blanchard) | Adapt leadership style to team member's maturity |
| OSCAR Coaching Model | Outcome, Situation, Choices, Actions, Review |
| Cynefin Framework | Simple / Complicated / Complex / Chaotic — guides decisions |
| Stacey Matrix | Certainty vs Agreement — when to use agile |
| VUCA Model | Volatility, Uncertainty, Complexity, Ambiguity — project environment |
| Organizational Change Models | Kotter 8-step, Prosci ADKAR, Lewin Unfreeze-Change-Refreeze |
VUCA — Key Definitions
VolatilityChange is rapid and unpredictable in nature and extent
UncertaintyLack of knowledge of issues and events; unclear causes
ComplexityMany interconnected parts making it hard to analyze
AmbiguityHaziness about reality; multiple interpretations possible
💡 Tip: VUCA environments → favor agile or adaptive approaches. High VUCA = more iterative planning, more stakeholder engagement.
🏢 Organizational Structures & PM Authority
| Structure | PM Authority | Resource Control | PM Role | Budget Control |
| Functional | Little to none | Functional Manager | Coordinator / Part-time | Functional Manager |
| Weak Matrix | Low | Mostly Func. Mgr. | Part-time | Functional Manager |
| Balanced Matrix | Medium (shared) | Shared | Full-time | Mixed |
| Strong Matrix | High | Mostly PM | Full-time | PM |
| Projectized | Full / Highest | PM | Full-time | PM |
| Composite | Varies | Varies | Varies | Varies |
⚠️ Trap: In a Balanced Matrix, the PM and Functional Manager have EQUAL authority. This creates the most conflict. Exam favorite scenario!
📌 Example: A PM complains they can't get engineers assigned to their project. → This is a Functional or Weak Matrix organization where functional managers control resources.
Tight Matrix ≠ Matrix Organization
Tight Matrix = co-location (war room). This is about physical space, NOT organizational structure. Don't confuse on the exam!
🏛️ PMO Types
| PMO Type | Authority Level | Role | Example Activity |
| Supportive | Low | Consultant / Repository | Provides templates, trains PMs |
| Controlling | Moderate | Compliance enforcer | Requires use of standard tools, audits |
| Directive | High | Direct management | PMO assigns and manages PMs directly |
💡 Tip: Think of it as: Supportive = library (take what you need). Controlling = compliance officer (must follow rules). Directive = boss (tells you what to do).
🗂️ Project vs Program vs Portfolio
| Level | Definition | Managed By | Focus |
| Project | Unique temporary work | Project Manager | Deliver defined scope |
| Program | Related projects managed together | Program Manager | Realize synergies & benefits |
| Portfolio | Strategic mix of work | Portfolio Manager | Align to organizational strategy |
📌 Example: A city builds a new transit system: Bridge Project + Tunnel Project + Station Projects = Program. All city infrastructure programs + roads + utilities = Portfolio.
Project vs Operations
| Project | Operations |
| Temporary with defined end | Ongoing, repetitive |
| Unique output | Standard, repeatable output |
| Ends when objectives met | Never ends (as long as org exists) |
| Example: Build a bridge | Example: Maintain a bridge |
⚖️ Project Governance
Project Governance = oversight structure ensuring the right decisions are made by the right people.
Key Governance Elements
- Steering Committee / Project Board — executive oversight; approves major decisions
- Change Control Board (CCB) — approves/rejects changes
- Sponsor — accountable executive; provides funding and direction
- Phase Gate / Stage Gate Review — go/no-go decision point at phase end
Phase Gate Reviews (Tollgates)
Phase Gates decide: Go / No-Go / Hold. The PM presents deliverables and metrics; the sponsor/steering committee decides.
💡 Tip: A project can be terminated at a phase gate even if it was running well — if the business case no longer applies. This is a correct and ethical decision.
💵 Project Selection Methods
Financial Analysis Models
| Method | Formula/Definition | Decision Rule |
| NPV | PV of benefits − PV of costs | Higher NPV = better; NPV > 0 = viable |
| IRR | Discount rate where NPV = 0 | Higher IRR = better; IRR > cost of capital |
| Payback Period | Initial Investment ÷ Annual Cash Flow | Shorter = better; faster recovery |
| BCR | Total Benefits ÷ Total Costs | BCR > 1 = viable; higher = better |
| Opportunity Cost | Value of next-best alternative foregone | Lower opportunity cost = better choice |
📌 Example: Project A: NPV=$500k · Project B: NPV=$300k → Select Project A (higher NPV).
Opportunity Cost of choosing A = $300k (value you gave up from B).
⚠️ Trap: If asked "Which project should be selected?" and one has higher NPV — always choose highest NPV. If asked "What is the opportunity cost of choosing Project A?" → it's the NPV of Project B (what you gave up).
Scoring Models (Non-Financial)
Weighted Scoring Model — assigns weighted scores across criteria (strategic fit, risk, ROI, urgency). Most comprehensive for project portfolio selection.
🏭 Make-or-Buy Analysis
Make-or-Buy Analysis is done during Plan Procurement Management.
| Make (Internal) | Buy (External) |
| Proprietary/sensitive technology | Specialized skills not available internally |
| Excess capacity available | Insufficient internal capacity |
| Control over quality needed | External costs are lower |
| Long-term strategic capability | Short-term or one-time need |
| IP protection critical | Faster time to market using vendor |
Break-Even Point = Fixed Cost of Making ÷ (Buy Cost per Unit − Variable Cost per Unit)
📌 Example: It costs $10,000 to set up internal production + $2/unit. Buying costs $7/unit. Break-even = $10,000 ÷ ($7−$2) = 2,000 units. If you need >2,000 → Make. If <2,000 → Buy.
📈 Benefits Realization Management
Benefits realization ensures the project delivers lasting value to the organization after the project closes.
Key Documents
| Document | Purpose | Created When |
| Business Case | Justify the project investment | Pre-project (before charter) |
| Benefits Management Plan | Define, track, and sustain benefits | During initiation/planning |
| Benefits Realization Report | Confirm benefits achieved | Post-project |
💡 Tip: Benefits are realized AFTER the project ends. The project manager hands off to operations who measure actual benefits. The sponsor is accountable for benefits realization.
👷 Resource Management Deep Dive
Resource Leveling vs Resource Smoothing
| Technique | Purpose | May Extend Schedule? | Constraint |
| Resource Leveling | Resolve over-allocation | YES — schedule may extend | Resource limits are fixed |
| Resource Smoothing | Optimize within schedule | NO — schedule kept | Float is used up |
Resource Histogram
Resource Histogram = bar chart showing resource demand over time. Bars above the availability line = overloaded = need leveling.
Halo Effect in Resource Decisions
Halo Effect = promoting the best engineer to PM just because they're a great engineer. Being good at a technical role ≠ PM skills.
Colocation vs Virtual Teams
| Aspect | Co-located | Virtual |
| Communication | Rich, face-to-face | Technology-dependent |
| Team culture | Easy to build | Requires extra effort |
| Collaboration tools | Whiteboard, war room | Video, Slack, Jira |
| Time zones | Not an issue | Major challenge |
| Cost | Higher (travel, office) | Lower overhead |
📊 RAM / RACI Matrix
RAM (Responsibility Assignment Matrix) — links WBS work to team roles.
RACI Definitions
| Letter | Role | Definition | How Many? |
| R | Responsible | Does the work | 1 or more |
| A | Accountable | Owns the outcome; signs off | Exactly 1 |
| C | Consulted | Input before decisions; 2-way comm. | 0 or more |
| I | Informed | Updated after decisions; 1-way comm. | 0 or more |
⚠️ Trap: There must be exactly ONE Accountable per task. Two people being accountable = no one is accountable. This is a common exam question!
📌 Example RACI:
| Activity | PM | Sponsor | Engineer | Client |
| Design review | A | I | R | C |
| Budget approval | R | A | I | I |
| Inspect deliverable | A | I | R | R |
🌐 Virtual & Distributed Teams
Key Challenges
- Time zone differences → scheduling conflicts
- Cultural differences → communication styles vary
- Technology reliance → tool failures disrupt work
- Trust building → harder without face-to-face time
- Isolation → reduced team cohesion and morale
PM Strategies for Virtual Teams
- Establish communication protocols and norms early
- Use video (not just audio) to increase connection
- Schedule overlap hours for synchronous collaboration
- Create virtual "water cooler" opportunities
- Celebrate wins publicly and frequently
- Use collaboration tools: Jira, Confluence, Miro, Teams, Slack
💡 Tip: The exam may say a virtual team member feels isolated. Best answer = increase communication frequency and find ways to build personal connection — not just add more meetings.
📋 Data Gathering Techniques
| Technique | Definition | Best Used For |
| Brainstorming | Generate ideas without judgment | Risk identification, requirements |
| Delphi Technique | Anonymous expert consensus (rounds) | Risk, estimation, forecasting |
| Interviews | One-on-one information gathering | Requirements, stakeholder needs |
| Focus Groups | Group discussion / attitudes | Requirements, customer feedback |
| Surveys/Questionnaires | Collect data from many people | Large stakeholder groups |
| Benchmarking | Compare to best practices | Quality, process improvement |
| Observation (Gemba) | Watch actual work being done | Process analysis, requirements |
| Nominal Group Technique | Brainstorm then vote to prioritize | Risk, decision making |
| Mind Mapping | Visual idea relationship diagram | Requirements, WBS creation |
| Affinity Diagram | Group ideas into themes | After brainstorming; risk grouping |
| Document Analysis | Review existing documents | Requirements, lessons learned |
💡 Tip: Delphi is anonymous → prevents dominant personalities from skewing results. Great for sensitive estimates. Exam frequently tests Delphi's key feature = anonymity.
🔬 Data Analysis Techniques
| Technique | Purpose | Where Used |
| Variance Analysis | Compare actual vs planned | Monitor & Control |
| Trend Analysis | Identify patterns over time | Monitor & Control |
| Earned Value Analysis | Integrate cost+schedule performance | Monitor & Control |
| Root Cause Analysis | Find underlying cause of problem | Quality, Risk, Issues |
| SWOT Analysis | Strategic + risk assessment | Risk identification, Planning |
| Assumption Analysis | Identify risks in assumptions | Risk identification |
| Regression Analysis | Predict future performance | Risk, Forecasting |
| Simulation (Monte Carlo) | Model probability of outcomes | Quantitative risk analysis |
| Sensitivity / Tornado Diagram | Rank risk impact on project | Risk prioritization |
🎲 Decision-Making Tools
| Tool | Use |
| Decision Tree | Evaluate options using EMV |
| Multicriteria Decision Analysis | Weighted scoring of options |
| Voting Methods | Group decisions |
| Autocratic Decision Making | Fast but low buy-in |
Voting Types
- Unanimity — everyone agrees (100%)
- Majority — more than 50% agree
- Plurality — largest block wins (no majority needed)
- Dictatorship — one person decides
💡 Tip: For planning poker and agile estimation, the team converges toward consensus — similar to unanimity / Delphi. Not a vote; a discussion to reach agreement.
🤝 Interpersonal & Team Skills
| Skill | Definition | Exam Context |
| Active Listening | Fully attend + paraphrase + clarify | Best for understanding stakeholders |
| Facilitation | Guide group to consensus | Meetings, workshops, conflict |
| Coaching | Develop individual skills | New or growing team members |
| Mentoring | Share experience; career guidance | Long-term development |
| Influencing | Get results without authority | Matrix orgs; cross-functional |
| Political Awareness | Understand formal & informal power | Stakeholder management |
| Cultural Awareness | Adapt to cultural differences | International / diverse teams |
⚠️ Trap: Coaching vs Mentoring: Coaching = skill development (shorter, task-focused). Mentoring = career guidance (longer, relationship-focused). Exam tests this distinction!
🤜🤛 Negotiation & BATNA
Negotiation is a key interpersonal skill for PMs — used with vendors, stakeholders, functional managers, sponsors, and team members.
Negotiation Approaches
| Approach | Description | Outcome |
| Win-Win (Integrative) | Collaborative; both parties benefit | Long-term relationships preserved |
| Win-Lose (Distributive) | Competitive; fixed pie divided | One party wins, other loses |
| Lose-Lose | Both parties over-compromise | Both dissatisfied |
BATNA — Best Alternative to Negotiated Agreement
BATNA = your best option if negotiations fail. Knowing your BATNA:
- Sets your walk-away point (don't agree to worse terms than your BATNA)
- Gives you negotiating confidence and leverage
- Prevents agreeing to a bad deal out of desperation
📌 Example: Negotiating with a contractor. Your BATNA = use an alternate vendor at $50k. If the contractor won't go below $60k, you walk away. The BATNA is $50k = your minimum acceptable outcome.
Key Negotiation Tactics to Know
- Anchoring — first offer sets the reference point
- Bracketing — start high, settle in the middle
- Deadlines — creating time pressure
- Good Cop/Bad Cop — one tough, one reasonable negotiator
🧠 Knowledge Management
Knowledge management is the process of capturing and using both explicit and tacit knowledge.
| Type | Definition | Examples | How to Capture |
| Explicit Knowledge | Documented, codifiable | Manuals, reports, lessons learned docs | Write it down; document it |
| Tacit Knowledge | Personal, experiential, hard to document | Expert judgment, know-how, intuition | Mentoring, communities of practice, shadowing |
💡 Tip: The hardest knowledge to transfer is tacit. When an experienced team member leaves, most of what's lost is tacit knowledge. Best capture method = pair them with less experienced members BEFORE they leave.
Lessons Learned Repository
- Part of OPA (Organizational Process Assets)
- Lessons learned are updated throughout the project, not just at close
- Future projects USE lessons learned from past projects as inputs
🔄 Organizational Change Management
Projects create change. The PM must help stakeholders transition from current state to the desired future state.
Kotter's 8-Step Change Model
- Create a sense of urgency
- Build a guiding coalition
- Form a strategic vision and initiatives
- Enlist volunteers in the change army
- Enable action by removing barriers
- Generate short-term wins
- Sustain acceleration — don't declare victory early
- Institute change — anchor in culture
ADKAR Model (Prosci)
| Letter | Element | Question It Answers |
| A | Awareness | Why is change needed? |
| D | Desire | Do I want to change? |
| K | Knowledge | How do I change? |
| A | Ability | Can I change? |
| R | Reinforcement | Will the change stick? |
⚠️ Trap: Stakeholder resistance is NOT always opposition to the project. It may be fear, lack of information, or uncertainty. The answer is usually to engage, communicate, and educate — not to escalate or force.
📏 Agile Estimation Techniques
| Technique | How It Works | Key Feature |
| Story Points | Relative complexity units assigned by team | Relative, not hours; team-specific |
| Planning Poker | Cards revealed simultaneously; discuss outliers | Prevents anchoring; consensus-driven |
| T-Shirt Sizing | XS / S / M / L / XL categories | Fast; good for large backlogs |
| Affinity Estimating | Silent grouping into size categories | Very fast; good for 50+ stories |
| Wideband Delphi | Anonymous rounds until consensus | Reduces bias; works for any method |
| Ideal Days | Uninterrupted work days | More intuitive than story points |
💡 Tip: Story points are NOT comparable between teams. Team A's story point ≠ Team B's story point. Never compare velocity across teams!
Fibonacci Sequence in Estimation
Planning poker uses Fibonacci numbers: 1, 2, 3, 5, 8, 13, 21, 34... Gaps increase with size to reflect increasing uncertainty in larger stories.
✅ Definition of Ready vs Definition of Done
| Concept | Definition | Applied To | Created By |
| Definition of Ready (DoR) | Story is ready to be worked on | Product Backlog items | Team + PO |
| Definition of Done (DoD) | Work is truly complete | Stories + Sprint Increment | Development Team |
Typical DoR Criteria
- User story written (As a… I want… So that…)
- Acceptance criteria defined
- Story sized/estimated
- Dependencies identified
- No blockers to starting
Typical DoD Criteria
- All acceptance criteria met
- Code reviewed and merged
- Unit tests written and passing
- Documentation updated
- Product Owner accepts the story
⚠️ Trap: The DoD is owned by the Development Team, not the Product Owner. But both agree on it. Stories not meeting DoD are NOT demo'd at Sprint Review.
🏢 SAFe — Scaled Agile Framework
SAFe scales agile to large enterprises with multiple teams working together.
SAFe Levels
| Level | Focus | Key Concept |
| Team | Individual Scrum/Kanban teams | Sprints, velocity |
| Program (ART) | Multiple teams aligned | PI Planning, Release Train |
| Large Solution | Very large, complex systems | Solution Train |
| Portfolio | Strategic alignment | Lean Portfolio Management |
Key SAFe Terms
- PI Planning — 2-day event for all teams to plan together (every 8-12 weeks)
- ART (Agile Release Train) — 50-125 people, multiple teams, single mission
- Program Increment (PI) — 8-12 week delivery cycle
⚡ XP & Other Agile Frameworks
XP — Extreme Programming
| XP Practice | Definition |
| TDD (Test-Driven Development) | Write tests first, then code to pass them |
| Pair Programming | Two devs at one workstation; driver + navigator |
| Refactoring | Continuously improve code without changing behavior |
| Continuous Integration (CI) | Merge code frequently; automate testing |
| Collective Code Ownership | Any dev can modify any part of code |
| Small Releases | Frequent small increments for fast feedback |
Other Frameworks at a Glance
| Framework | Key Idea |
| Crystal | Family of methods; scale by team size/criticality |
| DSDM | Fix time + budget; flex scope; never compromise quality |
| FDD (Feature-Driven Development) | Build by feature; design by feature |
| LeSS (Large Scale Scrum) | Multiple teams, one PO, one backlog |
🗓️ Agile Release Planning
Release Planning maps the Product Backlog to releases over time.
Forecasting Release Date
Number of Sprints = Total Story Points in Backlog ÷ Average Team Velocity
📌 Example: Backlog = 240 story points. Velocity = 40 points/sprint. Sprints needed = 240 ÷ 40 = 6 sprints. If each sprint is 2 weeks → release in 12 weeks.
Types of Roadmaps
| Type | Horizon | Detail Level |
| Product Roadmap | 6-18 months | Feature themes, not detailed stories |
| Release Plan | Next 3-6 months | Specific features per release |
| Sprint Plan | Next 1-4 weeks | Detailed user stories and tasks |
💎 Value-Driven Delivery
Agile prioritizes delivering the highest value items first so the customer gets maximum ROI even if the project is cut short.
Prioritization Techniques
| Technique | How It Works |
| MoSCoW | Must / Should / Could / Won't Have |
| Kano Model | Basic / Performance / Delight needs |
| Relative Weighting | Score value vs. cost to prioritize |
| WSJF (Weighted Shortest Job First) | Cost of Delay ÷ Duration = priority score |
MVP — Minimum Viable Product
MVP = smallest product that delivers value + enables learning. Not the cheapest version — the one that tests the core hypothesis with real users.
💡 Tip: Value-driven delivery means the PO should reorder the backlog based on business value. Highest ROI items always go to the top. The team never decides priority — the PO does.
📋 Source Selection Criteria
Source Selection Criteria — developed BEFORE receiving proposals so evaluation is objective.
Common Evaluation Criteria
| Criterion | What It Evaluates |
| Understanding of Need | Does the vendor understand your requirements? |
| Technical Capability | Can they technically do the work? |
| Management Approach | How will they manage the project? |
| Financial Capacity | Are they financially stable? |
| Past Performance | Track record on similar work |
| Price / Life Cycle Cost | Total cost including maintenance |
| IP Rights | Who owns deliverables and IP? |
Procurement Negotiation
Key items to negotiate: price, schedule, scope, quality, risk allocation, payment terms, IP ownership, warranties, penalties.
💡 Tip: Price is NOT always the most important selection criterion, especially for complex or high-risk contracts. Technical capability and past performance often weigh more.
⚖️ Claims Administration & Disputes
Claims Administration = managing contested changes in contracts.
Dispute Resolution Methods (in preferred order)
- Negotiation — direct resolution (fastest, cheapest)
- Mediation — neutral third party facilitates (non-binding)
- Arbitration — binding third-party decision (faster than court)
| Litigation | Court system — slowest, most expensive (last resort) |
⚠️ Trap: The exam prefers resolving disputes as early as possible, at the lowest level possible. Always try direct negotiation first before escalating.
📝 20 Advanced Scenario Questions
Scenario 1: PMBOK 7 Principle
📌 A PM adjusts the project life cycle mid-project from waterfall to hybrid because requirements are proving unclear. Which PMBOK 7 principle is applied?
✅ Tailoring — adapting the approach based on the project's specific context.
Scenario 2: Org Structure Conflict
📌 A PM cannot get engineers assigned because the Engineering Department Head says they're busy on other work. What type of organization is this?
✅ Functional or Weak Matrix — functional managers control resources, PM has low authority.
Scenario 3: PMO Role
📌 The PMO requires all projects to use the company's scheduling software, templates, and risk register format, and conducts quarterly audits. What type of PMO?
✅ Controlling PMO — requires compliance with standards; moderate control.
Scenario 4: Project Selection
📌 Project A: NPV=$200k, IRR=15%. Project B: NPV=$350k, IRR=12%. You can only do one. Which do you recommend?
✅ Project B — higher NPV means more value delivered. IRR alone isn't the deciding factor when NPV is available.
Scenario 5: RACI Issue
📌 During a review, it's found that both the PM and the Sponsor are marked "Accountable" for contract approval. What's the problem?
✅ There must be exactly ONE Accountable per task. Having two creates confusion and prevents clear ownership. Fix: remove one.
Scenario 6: Resource Leveling
📌 An engineer is assigned to two critical tasks simultaneously, creating overallocation. The PM uses resource leveling. What is the result?
✅ One task is delayed until the engineer is available. The project schedule may extend. Float may be consumed or critical path may change.
Scenario 7: Tacit Knowledge
📌 Your most experienced bridge inspector is retiring next month. How do you best capture their knowledge?
✅ Shadowing / mentoring / pair work — tacit knowledge can't be fully captured in documents. Have a junior inspector shadow them now.
Scenario 8: Change Resistance
📌 A key department is resisting adoption of the new system your project is delivering. What should the PM do first?
✅ Meet with department leaders to understand their concerns. Engage, listen, communicate benefits. Don't escalate or force compliance yet.
Scenario 9: Delphi Method
📌 A PM needs to estimate risk impacts but fears senior experts will dominate the process. Which technique is best?
✅ Delphi Technique — anonymous questionnaires prevent groupthink and dominant voices from skewing estimates.
Scenario 10: Contract Type Risk
📌 Scope is partially defined — you know what you want but not exactly how it will be delivered. Which contract type?
✅ FPIF (Fixed Price Incentive Fee) — seller has flexibility in approach but commits to a price ceiling. Incentive rewards performance.
Scenario 11: Agile Estimation
📌 During planning poker, one developer estimates 13 points while everyone else says 3. What is the right action?
✅ Ask the outlier to explain their reasoning. The outlier often knows something others don't. Discuss, then re-estimate. Don't just average.
Scenario 12: SAFe PI Planning
📌 Six teams are about to start a 10-week program increment. What event aligns them all to a shared plan?
✅ PI Planning — 2-day event where all ART teams plan together, identify dependencies, and commit to program increment objectives.
Scenario 13: DoD Not Met
📌 At Sprint Review, the team wants to demo a feature but code review hasn't been done. Should they demo it?
✅ No — if code review is part of the Definition of Done, the story is NOT complete. Incomplete items return to the Product Backlog.
Scenario 14: MoSCoW
📌 The team is running out of time. The PO needs to cut scope. Using MoSCoW, which items are dropped first?
✅ Won't Have → Could Have → Should Have. Must Have items are non-negotiable. Cut from the bottom up.
Scenario 15: BATNA
📌 You're negotiating with a vendor. They won't go below $80k but your BATNA is $70k with another vendor. What do you do?
✅ Walk away — the deal is worse than your BATNA. Exercise your best alternative.
Scenario 16: Virtual Team Trust
📌 A virtual team member in another country feels excluded and disengaged. Best PM action?
✅ Proactively increase one-on-one communication with the member, include them in decisions, find cultural bridge opportunities. Video calls preferred over email.
Scenario 17: Benefits Realization
📌 A project is complete and delivered on time/budget. 6 months later the sponsor reports the expected business benefits haven't materialized. Who is accountable?
✅ The Sponsor — benefits realization is the sponsor's responsibility, not the PM's. The PM delivered the project; the sponsor is accountable for benefits.
Scenario 18: Tailoring Decision
📌 A construction project has strict government regulations requiring detailed documentation and formal sign-offs at every phase. Which approach?
✅ Predictive / Waterfall — regulatory and compliance-heavy environments require predictive approaches with formal documentation and phase gates.
Scenario 19: Wideband Delphi
📌 A PM asks three experts independently to estimate task duration. Results: 5d, 9d, 14d. They discuss and re-estimate. This repeats until convergence. What technique?
✅ Wideband Delphi — structured rounds of anonymous estimation with discussion until consensus.
Scenario 20: Phase Gate
📌 At the end of Phase 2, the steering committee reviews the project. Market conditions have changed and the business case no longer holds. What should happen?
✅ Terminate the project at the phase gate. This is a legitimate and ethical decision. The PM closes the project properly with full documentation and lessons learned.
💡 25 More Power Tips
- PMBOK 7 = outcome-focused principles, not prescriptive processes
- Tailoring is NOT optional — you must tailor every project
- PMO Directive = highest authority; PMO Supportive = lowest
- Projectized org = PM has MOST authority; Functional = LEAST
- Balanced Matrix = most conflict between PM and Functional Manager
- Tight Matrix = co-location, NOT a type of matrix organization
- Benefits realization = sponsor's responsibility, not PM's
- NPV = best financial selection tool; higher is always better
- Opportunity Cost = value of the NEXT BEST alternative foregone
- Make-or-buy: calculate break-even to decide threshold
- Resource Leveling MAY extend schedule; Resource Smoothing does NOT
- Halo Effect = wrong reason to promote someone to PM
- RACI: only ONE Accountable per task — no exceptions
- Coaching = skill development; Mentoring = career development
- Delphi = anonymous to prevent groupthink/dominance
- Lessons learned = OPA; must be done THROUGHOUT project not just at end
- Tacit knowledge is harder to transfer than explicit knowledge
- ADKAR: if people lack Desire, training (Knowledge) won't help yet
- VUCA environment → prefer agile/adaptive approach
- PI Planning = SAFe's key event; all teams plan together
- Story points are team-specific; NEVER compare velocity across teams
- DoD must be met before demoing in Sprint Review
- MVP = smallest product that tests core hypothesis with real users
- MoSCoW: cut Won't Have first, then Could Have if more cuts needed
- Claims resolution order: Negotiate → Mediate → Arbitrate → Litigate
⚠️ More Exam Traps
| Trap | Students Choose | Correct Answer |
| Tight Matrix organization | A type of matrix org structure | Co-location (war room) — unrelated to org structure |
| Who is accountable for benefits realization? | Project Manager | Sponsor (after project close) |
| Two people listed as Accountable in RACI | That's fine — shared accountability | ERROR — only ONE Accountable allowed |
| Resource Leveling | Never changes the schedule | It MAY extend the schedule |
| Resource Smoothing | May extend the schedule | Does NOT extend schedule; uses float only |
| Best way to capture expert's tacit knowledge | Ask them to document it | Shadowing, mentoring, pair working |
| Opportunity Cost of choosing Project A | Total cost of Project A | Value of the NEXT BEST option you gave up |
| Story points can compare team performance | Yes — higher velocity = better team | No — story points are team-specific; never compare |
| Incomplete story at Sprint Review | Demo it but note it's incomplete | Do NOT demo; return to Product Backlog |
| Stakeholder is resistant — best action? | Escalate to their manager | Meet 1:1 to understand concerns; engage and educate |
| Project terminated at phase gate | PM failed; project was cancelled | Correct governance — business case no longer valid |
| NPV vs IRR — which to use? | IRR — higher % sounds better | NPV — measures actual value added in dollars |
| Coaching vs Mentoring | Same thing | Coaching = skill/task focus; Mentoring = career/long-term |
| PMBOK 7 Knowledge Areas | Same as PMBOK 6 | PMBOK 7 replaced KAs with 8 Performance Domains |
🔑 More Power Keywords
Click any keyword for explanation:
Stewardship
Systems Thinking
VUCA
Cynefin
Stacey Matrix
Phase Gate
Program
Portfolio
PMO-Supportive
PMO-Controlling
PMO-Directive
NPV
IRR
BCR
Opportunity Cost
Resource Leveling
Resource Smoothing
Halo Effect
Active Listening
BATNA
Win-Win
Explicit Knowledge
Tacit Knowledge
ADKAR
Kotter 8-Step
Story Points
Planning Poker
Definition of Ready
Definition of Done
PI Planning
ART
TDD
Pair Programming
MVP
MoSCoW
WSJF
Kano Model
Source Selection Criteria
Claims Administration
Arbitration
Benefits Mgmt Plan
Tailoring