📋 PMP 49 Processes — Master Course Complete Interactive Study Guide | Eng. Ahmad Safi, PE

🎯 What Are the 49 PMP Processes?

The PMBOK® Guide (6th Edition) organizes project management into 49 processes across 5 Process Groups and 10 Knowledge Areas.

Initiating (2)
Planning (24)
Executing (10)
Monitoring & Controlling (12)
Closing (1)

🚀 Initiating (2)

  • Develop Project Charter
  • Identify Stakeholders

Start of project or phase. Sponsor authorizes.

📋 Planning (24)

Largest group! Creates all baselines & management plans. 24 = more than all others combined.

⚙️ Executing (10)

Do the real work! Where most change requests are generated.

📡 M&C (12)

Compare actual vs plan. Runs THROUGHOUT the project. Generates change requests when variances found.

✅ Closing (1)

  • Close Project or Phase

Formal acceptance, archive, release team.

📚 10 Knowledge Areas

  • 1. Integration (7)
  • 2. Scope (6)
  • 3. Schedule (6)
  • 4. Cost (4)
  • 5. Quality (3)
  • 6. Resource (6)
  • 7. Communications (3)
  • 8. Risk (7)
  • 9. Procurement (3)
  • 10. Stakeholder (4)
⚡ Top Exam Facts
🔴 FACT 1: Planning has 24 processes — the most of any group. The exam loves to test WHICH group each process belongs to.
🔴 FACT 2: Integration & Risk Management BOTH have 7 processes — the most of any knowledge area.
🔴 FACT 3: Integration Management is the ONLY KA with processes in ALL 5 groups.
🔴 FACT 4: Monitoring & Controlling runs PARALLEL to all other groups throughout the project.
🔴 FACT 5: Work Performance DATA (raw) → Work Performance INFORMATION (analyzed) → Work Performance REPORTS (formatted). Know this flow!
🔴 FACT 6: Verified Deliverables (from Control Quality) → Accepted Deliverables (from Validate Scope). ORDER matters!
🔴 FACT 7: Close Project is the ONLY Closing process. Even CANCELLED projects must be formally closed.
🧮 Count Quick-Reference
Knowledge AreaIPEM&CCTotal
Integration112217
Scope-4-2-6
Schedule-5-1-6
Cost-3-1-4
Quality-111-3
Resource-231-6
Communications-111-3
Risk-511-7
Procurement-111-3
Stakeholder1111-4
TOTAL2241012149
📊 Official PMBOK 5x10 Process Matrix

Click any process cell to open its full detail. This is the exact grid from the PMBOK Guide — memorize it!

STUDY TIP: Cover one column at a time and recite each process. Then cover one row and recite the process group. Do this daily for 1 week.
🔎 Filter View by Knowledge Area
🔍 Browse All 49 Processes

Cards marked ✓ are studied. Click any card for full detail.

📄 Master Cheat Sheet — All 49 Processes
PRINT TIP: Print this page. Cover the Process Group column and test yourself. Then cover the Knowledge Area. Then cover Key Output.
#Process NameKnowledge AreaProcess GroupKey Output(s)Exam Hot Point
📌 Inputs Flow Summary
RULE: Outputs of earlier processes become Inputs to later ones. Here are the most critical hand-offs:
Output FROMBecomes Input TOWhat it is
Develop Project CharterAlmost ALL planning processesProject Charter provides authorization & high-level info
Control QualityValidate ScopeVerified Deliverables (internal check done, now needs customer acceptance)
Validate ScopeClose Project or PhaseAccepted Deliverables (formally signed off by customer)
Identify RisksAll other Risk processesRisk Register (first created, then updated continuously)
Direct & Manage WorkMonitor & Control WorkWork Performance Data (raw) → becomes Information
Monitor & Control WorkPerform Integrated Change ControlWork Performance Reports + Change Requests
Create WBSDefine ActivitiesWork Packages decomposed into Activities
Estimate Activity DurationsDevelop ScheduleDuration Estimates used to build the schedule
Determine BudgetControl CostsCost Baseline (S-Curve) for comparison
📈 EVM & Key PMP Formulas

🏭 Core EVM Formulas — MUST MEMORIZE ALL

🔢 EVM Calculator — Practice Tool




🔤 PERT Formula & Estimating Techniques
TechniqueFormula / MethodAccuracyWhen UsedExam Tip
PERT(O + 4M + P) / 6MediumWhen range is availableStd Dev = (P-O)/6; Variance = [(P-O)/6]²
AnalogousSimilar past project dataLow (-25% to +75%)Early/concept phaseTop-down, fastest, least accurate
ParametricUnit rate × quantityMediumWhen unit costs are knownE.g. $180/CY × 500 CY = $90,000
Bottom-UpSum of all work packagesHigh (-5% to +10%)Detailed/execution phaseMost accurate, most time-consuming
ROMRough Order of MagnitudeVery Low (-25% to +75%)Concept/initiationUsed in charter/early decisions
📈 PERT Practice Calculator



📋 Communication Channels Calculator
📋 Contract Types Comparison
MASTER RULE: Fixed Price contracts = SELLER bears risk. Cost Plus contracts = BUYER bears risk. T&M = shared/medium risk. Always remember who bears the risk!
Contract TypeAbbrev.Who Bears RiskBest Used WhenKey FeatureExam Tip
Firm Fixed PriceFFPSellerScope is well-definedPrice locked in; seller absorbs overrunsMost common, least risk for buyer
Fixed Price Incentive FeeFPIFSeller (mostly)When you want seller to perform betterProfit sharing for beating targetsPoint of Total Assumption (PTA) formula!
Fixed Price Economic Price AdjustmentFP-EPASellerLong-term contracts with inflation riskPrice adjusts with inflation indexUsed for multi-year contracts
Time and MaterialsT&MSharedSmall/short scope not fully definedPay per hour + materialsHybrid; used for staff augmentation
Cost Plus Fixed FeeCPFFBuyerResearch/innovative work, scope unclearCost reimbursed + fixed feeMost risk for buyer; seller has no incentive to be efficient
Cost Plus Incentive FeeCPIFBuyer (mostly)When performance incentives matterCost + fee that grows if targets beatSeller motivated to perform well
Cost Plus Award FeeCPAFBuyerWhen subjective performance mattersAward fee based on buyer judgmentBuyer has most discretion; not easily disputed
PTA Formula (FPIF): PTA = [(Ceiling Price - Target Price) / Buyer's Share Ratio] + Target Cost
⚠️ Risk Response Strategies
Risk TypeStrategyWhat It MeansExampleExam Tip
THREATS
(Negative Risks)
AvoidEliminate risk by changing planChange design to avoid unstable soil zoneBest strategy if high P & I
TransferShift impact to 3rd partyBuy insurance; include penalty clause in contractDoesn't eliminate risk, just moves $
MitigateReduce probability or impactAdd redundant equipment to reduce breakdown impactMost common strategy
AcceptAcknowledge and accept riskActive: set contingency reserve. Passive: do nothingUsed for low P×I risks
OPPORTUNITIES
(Positive Risks)
ExploitMake sure opportunity happensAssign best engineer to ensure early finishOpposite of Avoid
ShareGive part of opportunity to 3rd partyJoint venture to capture new marketOpposite of Transfer
EnhanceIncrease probability or impactAdd resources to increase chance of early finish bonusOpposite of Mitigate
AcceptTake advantage if it occursNo active plan; just wait and benefitSame word, same concept for both
👥 Organizational Structure Impact on PM Authority
Org TypePM AuthorityResource ControlPM RoleBudget Control
FunctionalLittle/NoneFunctional ManagerPart-time coordinatorFunctional Manager
Weak MatrixLimitedMostly Func. MgrPart-timeFunctional Manager
Balanced MatrixLow-ModerateMixedFull-timeMixed
Strong MatrixModerate-HighMostly PMFull-timePM
ProjectizedHigh/FullPMFull-timePM
👥 Conflict Resolution Methods (Best to Worst)
RankMethodAlso CalledOutcomeWhen to Use
#1 BESTConfront / Problem-SolveCollaboratingWin-WinAlways first choice on exam
#2Compromise / ReconcileNegotiatingLose-Lose (partial)Both parties give something up
#3Smooth / AccommodateYieldingTemporaryMaintain relationship short-term
#4Force / DirectCompetingWin-LoseOnly in emergencies
#5 WORSTWithdraw / AvoidRetreatingLose-LoseNever best; just delays conflict
🌟 Motivation Theories Quick Ref
TheoryAuthorKey ConceptExam Application
Hierarchy of NeedsMaslow5 levels: Physiological → Safety → Social → Esteem → Self-ActualizationLower needs must be met before higher ones motivate
Theory X vs YMcGregorX: workers lazy & need control. Y: workers motivated & self-directPM should assume Theory Y; use participative style
Hygiene vs MotivatorsHerzbergHygiene (pay, safety) prevents dissatisfaction. Motivators (achievement) cause satisfactionSalary alone doesn't motivate — it just prevents unhappiness
Achievement TheoryMcClellandnAch (achievement), nAff (affiliation), nPow (power)High achievers prefer challenging work and feedback
Expectancy TheoryVroomMotivation = Expectancy × Instrumentality × ValencePeople work hard if they believe effort leads to reward they value
🧠 Memory Tricks & Mnemonics

🔢 Count: 2-24-10-12-1

"I Plan Every Monday Carefully"
Initiating=2 | Planning=24 | Executing=10 | M&C=12 | Closing=1

📚 10 Knowledge Areas

"I Should Start Careful Quality Reviews. Can Projects Run Smoothly?"
Integration • Scope • Schedule • Cost • Quality • Resource • Communications • Procurement • Risk • Stakeholder

🔗 Integration (7): D-D-D-M-M-P-C

"Dogs Don't Dash; Most Must Play Calm"
Develop Charter • Develop PM Plan • Direct & Manage Work • Manage Knowledge • Monitor & Control Work • Perform Integrated Change Control • Close Project

📒 Scope (6): P-C-D-C-V-C

"Please Call Dave. Create Very Clear scope."
Plan Scope Mgmt • Collect Requirements • Define Scope • Create WBS • Validate Scope • Control Scope

📅 Schedule (6): P-D-S-E-D-C

"Please Don't Skip Every Day, Coach!"
Plan Schedule • Define Activities • Sequence Activities • Estimate Durations • Develop Schedule • Control Schedule

💰 Cost (4): P-E-D-C

"Please Estimate Daily Costs"
Plan Cost • Estimate Costs • Determine Budget • Control Costs

✅ Quality (3): P-M-C

"Plan, Manage, Check"
Plan Quality • Manage Quality • Control Quality
KEY DISTINCTION: Manage = process audit. Control = product inspection.

👥 Resource (6): P-E-A-D-M-C

"Plan Early, Acquire Dedicated, Manage Carefully"
Plan Resource • Estimate Resources • Acquire Resources • Develop Team • Manage Team • Control Resources

📞 Communications (3): P-M-M

"Plan, Manage, Monitor"
Plan Comm • Manage Comm • Monitor Comm
FACT: PM spends 90% of time communicating!

⚠️ Risk (7): P-I-Q-Q-P-I-M

"Please Identify Quick Quirks; Plan Is Mandatory"
Plan Risk • Identify Risks • Qualitative • Quantitative • Plan Responses • Implement Responses • Monitor Risks
NOTE: Qualitative always comes before Quantitative!

📋 Procurement (3): P-C-C

"Plan, Conduct, Control"
Plan Procurement • Conduct Procurements • Control Procurements
NOTE: Contracts are CLOSED in Control Procurements, not Close Project!

👥 Stakeholder (4): I-P-M-M

"Identify, Plan, Manage, Monitor"
Identify Stakeholders • Plan Engagement • Manage Engagement • Monitor Engagement
NOTE: Identify is in INITIATING — very important!

⚡ Risk Response Mnemonics

Threats: ATMA"Avoid Tigers, Mitigate Attacks" (Avoid, Transfer, Mitigate, Accept)
Opportunities: ESEA"Exploit Shared Enhancements Always" (Exploit, Share, Enhance, Accept)

🧠 Tuckman Team Stages

F-S-N-P-A: "Forming Soldiers Never Panic Anymore"
Forming • Storming • Norming • Performing • Adjourning
EXAM: Conflict peaks in STORMING. Best performance in PERFORMING.

💰 Reserve Types

Contingency Reserve = PM controls = for KNOWN unknowns = IN the cost baseline
Management Reserve = Sponsor controls = for UNKNOWN unknowns = OUTSIDE the baseline
"PM knows the Contingency; Sponsor holds the Management"

📈 EVM Signs Quick Reference

CV/SV Positive = GOOD. Negative = BAD.
CPI/SPI >1 = GOOD. <1 = BAD.
CV = EV-AC (cost). SV = EV-PV (schedule).
CPI = EV/AC (cost). SPI = EV/PV (schedule).
"EV is always in the numerator and the first term!"

📋 Scope Baseline = 3 Things

"WBS + WBS Dictionary + Project Scope Statement"
Many students forget the Project Scope Statement is part of the baseline!
Schedule Baseline = Approved schedule model
Cost Baseline = Time-phased budget (S-Curve)

⚡ Flashcard Drill — Click to Flip

Click the card to reveal the answer. Use arrow buttons to navigate. Card 1 of 0

Loading...

Answer:

Card Set:
Study Log: Cards viewed: 0
❓ PMP 49 Processes Quiz
0
Total Q's
0
Correct
0
Wrong
0%
Score
Topic:
📝 My Personal Study Notes

Auto-saved to this browser every keystroke. Your notes persist between sessions.

Auto-saved ✓
📌 Process-Specific Notes
Auto-saved ✓
📃 Study Summary (Auto-Generated)
📈 My Study Progress

0 / 49 processes studied (0%)

📊 By Process Group
📚 By Knowledge Area
🎯 Study Recommendations